Eighth Seismic Crew
General information about the project
- The (2D) North Qahtan Program is located within the administrative boundaries of Ninawa Governorate in the northwestern of Iraq and west of Ninawa Governorate. It is located (125) km from Ninawa Governorate and includes several villages and residential complexes. The total area of the program is (860.3) km.
Program name / Country North Qahtan / Iraq
Program Location / Governorate Al-Mosul
Beneficiary / North Oil Company
Implementing crew/ Eighth Seismic Crew
Crew Type / Vibratory
Camp Type / Mobile - Caravan
Survey Type / (2D) Vibratory
Transition Date to the Program / From Sasan Tala’far Camp
Field Testing Date / 27/8/2025
Surveying Commencement Date / 15/8/2025
Registration Start Date / 27/8/2025
Registration End Date / 26/11/2025
Project Size / 747.85 km/length
Total Number of Program Points / 14957 power point
Number of Points Recorded During 2025 / 14918
Size of Part Implemented During 2025 / 745.9 km/length
Program Completion Percentage / 99%